Provided preconstruction, construction, and closeout services related to the seismic retrofit of an existing concrete gymnasium, which included:
Construction Estimating
Preconstruction and estimating
Development of Project Schedule
Infilling of existing openings in the concrete structure
Pouring concrete footings for “strongbacks”
Crane-erecting of new steel “strongbacks” on the interior of the gymnasium for the purpose of bracing the existing concrete structure
Rehabilitation of existing timber roof trusses
New roofing package
Seismically isolating adjacent structures to the gymnasium
PROJECT DETAILS
CLIENT:
Harrisburg School District #41
LOCATION:
642 Smith St.
Harrisburg, OR 97446
ARCHITECT/ENGINEER:
ZCS Engineering
127 NW D St.
Grants Pass, OR 97526
SIZE/COST:
$1.2 Million
PROJECT TYPE:
CM/GC Preconstruction/Construction Method